Stryker (Cooling Towers)

Customer: Stryker, Arroyo

Project Title: Cooling Towers Replacement

Year: 2018

Type of Project:

  • Mechanical
  • Electrical
  • General Construction

Customer Issues/Needs:

  • Removal of two (2) old Cooling Towers
  • Installation of two (2) new 600 Ton Stainless Steel Cooling Towers

Project Highlights:

  • Cooling towers structural bases modification
  • Seismic support installation
  • Rigging of old & new cooling towers
  • Supply and install:
    • 10″ & 12″ SCH 40 carbon steel piping
    • Balancing valves
    • Isolation valves
    • Electrical NEMA 4X for fans
    • Drain lines & 2″ stainless steel make-up water supply lines

Before and After Images:

Old Cooling Towers
Rigging: 1st old cooling tower
Left: Rigging 2nd old cooling tower
Right: 1st new cooling tower in place
Rigging: 2nd new cooling tower
New Cooling Towers in Place

Contact ESCOPR at 787-782-7103 to request a FREE Energy Audit and begin receiving savings immediately!

Share this post

Share on facebook
Share on twitter
Share on linkedin
Share on print
Share on email
Recent Posts
Close Menu